Sidewalk replacement and road re-paving is set to begin Monday August 15, 2011 along South Bayview. The supervisor of the work Bruce Shaw tells The South Bayview Bulldog that access to all shops will be maintained during sidewalk work. It’s expected to be finished by Friday, September 9, 2011. Most pleasantly, there will be no work on Saturday or Sunday when shoppers will be able to park free on South Bayview. Many will wipe away a tear to see the removal of flowers so carefully planted this spring. But everything is going. Concrete boxes and trees too. Trees will be planted in underground boxes with grating to permit water to flow. Sorry for the previous error now corrected re date of work.
how can the work start on september 15th and end on september 9th? Is it going to take a whole year?