- Sutherland Drive from Millwood Road to Astor Avenue (Road Rehabilitation)
- Millwood Road from Mount Pleasant Road to Forman Avenue (Road Rehabilitation)
- McRae Drive from Crandall Road to Rumsey Road (Road Resurfacing)
- Belsize Drive from Harwood Road to Boyton Road (Road Resurfacingin)
Belsize Drive from Boyton Road to Thurston Road (Road Rehabilitation) - Rumsey Road from McRae Drive to Sharron Drive (Road Reconstruction)
Rumsey Road from Heath Road to McRae Drive (Road Resurfacing)
Category: 2024 Road Works
Even more road works planned for Leaside and Davisville
by
•Start Date: April 1, 2024 End Date: October 31, 2024
The City of Toronto is planning to rehabilitate Sutherland Drive from Millwood Road to Astor Avenue. Inspection of the road shows that it needs rehabilitation and sections of damaged curb and sidewalk need to be replaced to bring them to a state of good repair. Low amounts of asbestos have been detected in the asphalt roadway which will be removed and disposed by the contractor as per City protocols. Residents should expect minimal delays when traveling through the area. We appreciate your patience with the dust, noise, fencing and other inconveniences. This project is part of the Council-approved 2024 Capital Works Program to renew aging City roads and sidewalk for current and future needs.
Road Rehabilitation on Millwood Rd from Mount Pleasant Rd to Forman Ave
Start Date: April 1, 2024 End Date: October 31, 2024
The City of Toronto is planning to rehabilitate Millwood Road from Mount Pleasant Road to Forman Avenue. Inspection of the road shows that it needs rehabilitation and sections of damaged curb and sidewalk need to be replaced to bring them to a state of good repair. Low amounts of asbestos have been detected in the asphalt roadway which will be removed and disposed by the contractor as per City protocols. Residents should expect minimal delays when traveling through the area. We appreciate your patience with the dust, noise, fencing and other inconveniences. This project is part of the Council-approved 2024 Capital Works Program to renew aging City roads and sidewalk for current and future needs.
But wait, there’s more… road works for Leaside in 2024
by
•Further to our post earlier this week about proposed road work in the area, we have two more streets to add to the list.
Road Resurfacing on McRae Drive from Crandall Road to Rumsey Road
Start Date: April 2024 End Date: October 2024
The City of Toronto is planning to resurface McRae Road from Crandall Road to Rumsey Road. Inspection of the road shows that it needs repaving, and sections of damaged curb and sidewalk need to be replaced to bring them to a state of good repair.
Road Reconstruction on Rumsey Road from McRae Drive to Sharron Drive and Road Resurfacing on Rumsey Road from Heath Road to McRae Drive
Start Date: April 2024 End Date: October 2024
The City of Toronto is planning to reconstruct Rumsey Road from McRae Drive to Sharron Drive and resurface Rumsey Road from Heath Road to McRae Drive. Inspection of the road shows that the section from McRae Drive to Sharron Drive needs reconstruction and the curb and sidewalk need to be replaced while the section from Heath Road to McRae Drive needs repaving, and sections of damaged curb and sidewalk need to be replaced to bring them to a state of good repair.
Bayview-Leaside commuters face impact of 2024 road work
by
•Road Resurfacing on Bayview Avenue, from Roehampton Avenue to Armistice Drive
Start Date: April 2024 End Date: September 2024 (Timeline is subject to change.)
In May 2023, the City notified residents of this planned work, however due to delays encountered with the tender and award process the work was deferred to Spring 2024. The City of Toronto is planning to resurface Bayview Avenue from Roehampton Avenue to 30 m north of Armistice Drive. Inspection of the road shows that it needs repaving, and sections of damaged curb and sidewalk need to be replaced to bring them to a state of good repair. The City will also perform traffic signal upgrades at all Bayview Avenue signalized intersection within project limits. View full notice.
Road Reconstruction and Road Safety Improvements on Millwood Road, Pape Avenue and Donlands Avenue
Start Date: Mid-April 2024 End Date: December 2024 (Timeline ls subject to change.)The City of Toronto is planning state-of-good-repair work on Millwood Road, Pape Avenue and Donlands Avenue due to the poor condition of the roads. This project is part of the Council-approved 2024 Capital Works Program to renew aging City roads and sidewalk for current and future needs. More info at toronto.ca/millwood